Inmos Microprocessor Factory
The concept for INMOS is large, column-free flexible and universally serviced open operational spaces with a central circulation spine and central meeting space at its heart.
The fast-track nature of the project required the design to be responsive to any site and capable of being built in a range of sizes. The factory is located at Newport, Gwent, close to major transport routes. The 8,900 m2 building provides office and ancillary space, plus facilities for microchip wafer production.
Speed of design and construction were critical factors. The single-storey steel structure was conceived as a kit of parts, with maximum off-site prefabrication allowing the building to be erected bay by bay. The structure is a tubular steel assisted span-tension structure, supported by tension tie rods from the spine towers. This system provides uninterrupted column-free spaces for maximum internal flexibility. The roof is fabricated from 6m span steel decking with thermal insulation and a five-layer roof membrane. The external walls are based on a system of standardised mullions incorporating various infills: single glazing, double glazing, translucent or opaque panels. Wall performances and finishes can be varied as required. The initial design includes double glazing for office areas and solid insulated sandwich panels for production areas.
The building features a central circulation/service spine with internal wings for specialised activities. The spine is 7.2 m wide and 106 m long and acts as an internal street, wide enough for vending machines, public telephones, seating, meeting places, planted areas and waiting areas. Services from the plant room – hot and cold water, chilled water, compressed air, etc – run at high level in this main spine. The building is extendable along the spine in 13 x 36m bays. Offices and restaurants are on the south side of the spine and the clean room production area to the north. Production wastes are collected in linear floor trenches and supply services are distributed on service walls. A large clean room facility and shipping and receiving bays occupy the north side of the spine. The south side has one bay omitted, providing a landscaped courtyard between the offices and the restaurant. Assembly labs and main piped services plant room occupy three western bays of the south face.
Project information:
- Place: Newport, Wales
- Date: 1982 - 1987
- Client: Inmos Ltd
- Area: 8,900 m²
- Architect: Richard Rogers Partnership
- Structural Engineer: Anthony Hunt Associates
- Services Engineer: YRM Engineers
- Quantity Surveyor: GA Hanscomb Partnership
- Main Contractor: Laing Management Contracting Ltd
Awards:
- The Structural Steel Design Award, 1982
- Eurostructpress Award, 1983
- Financial Times Architecture at Work Award Commendation, 1983
- Constructa-Preis for Overall Excellence in the Field of Architecture, 1986
--Rogers Stirk Harbour + Partners 14:09, 12 March 2015 (UTC)
Featured articles and news
UK Net Zero Carbon Buildings Standard V1 published
Free-to-access technical standard to enable robust proof of a decarbonising built environment.
Prostate Cancer Awareness Month
Why talking about prostate cancer matters in construction.
The Architectural Technology podcast: Where it's AT
Catch up for free, subscribe and share with your network.
The Association of Consultant Architects recap
A reintroduction and recap of ACA President; Patrick Inglis' Autumn update.
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.